Tuesday, 8 May 2012

Learning Curves

Overview

  • The resources required to produce the given amounts of a product tend to decline as output accumulates
  • Cause of decline -- > learning curve. Workers become more adept at a task the more they perform it. This is measured mathematically
  • Cumulative average time per unit/batch decreases by a fixed percentage each time the cumulative production doubles
  • Learning rate = %

When does learning curve theory apply?
  • Labor intensive - product made largely by labor effort
  • New - brand new or relativity short-lived product
  • Complex - product made in small quantities for special orders




Example 1

A firm with a learning rate of 80% takes 50 hours to make its first unit. It has now made a total of 16 units. How long will the next 16 units take?


Formula Approach


Example 2

  • Derive the formula for the 80% learning rate and apply it to confirm the cumulative average time per unit for 16 batches in the previous illustration
  • Using the same formula, calculate the cumulative average time per unit for 20 batches
  • The formula is calculated as follows:
    • b = log 0.8/log 2 = -0.322
    • y = ax -0.322
    • At 16 batches: 50 x 16 -0.322 = 20.48
    • At 20 batches: 50 x 20 -0.322 = 19.06

Uses of the learning curve
  • Price setting
  • Budget setting
  • Production scheduling
Limitations of learning curve theory
  • Not always present
  • Assumes stable conditions which allow learning to take place
  • Assumes certain degree of motivation among employees
  • Breaks between repeating production of an item must not be too long or workers will forget and learning will have to begin again
  • Maybe difficult to obtain enough accurate data to decide what learning factor is
  • Learning is eventually cease
Practice Test

36 Batch Processing (10 Marks)
  • Standard direct labor cost of one batch of 100 units of product is $50.40
  • Standard time of 4.2 hours @ $12 per hour, with average time expected per batch based on product life of 12,800 units or 128 batches
  • Expected time for the first batch was 20 hours and an 80% learning curve
  • Company already completed 32 batches with total actual direct labor cost of $3,493
  • Direct labor variances:
    • Direct labor rate = $85 adverse
    • Direct labor efficiency = $891 adverse
  • Required:
    • Actual rate of learning
    • Total direct labor cost
  • Answers:
a) Y = axb
  • Standard cost of actual labor hours worked is actual cost less the adverse direct labor rate variance
    • $3,493 - $85 = $3,408
  • Actual labor hours worked is $3,408/$12 = 284 labor hours
  • Hours per batch = 284/32 = 8.875 hours per batch
  • Learning rate = 5√(8.875/20) = 0.85 = 85% --> 32 batches represents 5 doublings of output
b) Total direct labor cost

  • Actual labor rate is $3,493/284 = $12.30 per hour
  • b = log .85/log 2 = -0.2345
  • Average time: Y = axb
    • 20 X 128 -0.2345 = 6.41 hours
  • Total cost = average time x no. of batches x actual labor rate
      • 6.41 x 128 x $12.30
      • $10,092

37 The Learning curve effect
  • Actual output is 560 units, 3500 hours at a cost of $57,750
  • Standard time of 8 hours @ $15 per hour
  • Expected time for the first 600 units was 8 hours and an 90% learning curve
  • Direct labor variances:
    • Direct labor rate = $5,250 adverse
    • Direct labor efficiency = $14,700 Favourable
  • Required:
    • Planning and Operating variances
    • Importance of learning curves in the context of Target costing
    • 90% learning index of -0.1520
  • Answers:
a) Y = axb
  • Y = 8 X 560 -0.1520 = 3.057 hours
    • Total time for 560 units (560 X 3.057 hours) = 1,712 hours










2 comments:

  1. wonderfully explained. use of Excel makes it so easy. studies has become so pleasurable. only that there are few takers (atleast where I stay, kolkata).

    ReplyDelete